Lambda misses a Texas lease deadline, letting either side cancel $34.9 billion of its Anthropic compute deal; Anthropic says it will stayReported
Lambda did not secure a data center lease by the deadline in its roughly $41.3 billion August agreement with Anthropic, so either party can now end the $34.9 billion GPU cloud portion, which was meant to supply about 350 MW of Nvidia capacity at Hut 8's Beacon Point site in Texas, TokenPost reported. Anthropic said on Nov. 10 that it does not plan to terminate the deal. The lease condition was already disclosed in Anthropic's IPO filings.
Why it matters
Compute deals this large are central to Anthropic's IPO story, and this one is now cancellable at will.