OpenAI launches a Grid Protectors Program, letting Georgia Power cut up to 1,000 MW from its Effingham campus at peak times
OpenAI said its future data centers will reduce power use when local grids are strained, starting with its planned 3.2 GW campus in Effingham County, Georgia, where a 25-year Georgia Power deal approved in August allows cuts of up to 1,000 MW. Terms will be set with each utility and some sites may supply on-site generation or batteries; OpenAI also says it will pay for the lines and service its campuses need. OpenAI concedes flexibility does not replace new plants and transmission.
Why it matters
Data center power demand is a growing local fight, and this is OpenAI's offer to ease it.